Power supply[Nicht freigegeben][Bisher nicht für die Übersetzung exportiert]
- Strip the supply line.
- Strip the conductors 10 mm.
When routing the supply line, comply with the permissible bending radius. |
Single-phase operation
- Connect the conductors of the supply line to the terminals L1, N and PE as per the terminal labelling.
- Comply with the connection data for the terminals.
To operate the product in single-phase mode, a change in the configuration tool is also required ("Connected phases" parameter).
Three-phase operation
- Connect the conductors of the supply line to the terminals L1, L2, L3 N and PE as per the terminal labelling.
- Comply with the connection data for the terminals.
Power supply connection for solar charging
MENNEKES recommends connecting the L1 phase of the charging station to the same phase of a single-phase feeding inverter. In this way, an unbalanced load can be avoided. |