Configuring the product
The tasks described in this section may only be carried out by a qualified electrician. |
In the top section of the housing, there are two 8-pin DIP switches, with which the device can be configured. In the delivery state, all DIP switches are switched off ("OFF"). On delivery, the product is ready for connection.
1 | Bank S1 |
2 | Bank S2 |
The following functions can be set via the DIP switches:
Bank S1
DIP switch | Function |
---|---|
1 | LED display colour scheme
|
2 | Unbalanced load limitation
|
3 | Authorisation
|
4, 5, 6, 7, 8 | Without function |
3 | Authorisation
|
4 | Using Modbus RTU
|
5 | Master / Satellite
|
6 | Type of energy meter
|
7 | Solar charging
|
8 | Without function |